The Philippine Star published the following figures and delivery dates for the indicated CUP Phase 2 projects. An older PIA article, however, stated that the total number of rocket launchers was “335”
Project | Quantity | Value | Expected delivery date |
Multi-purpose rocket launcher | 335 | P37,440,000.00 | October 2012 |
81mm mortar with ammunition | 100 units w/ 2,000 rounds | P190,320,000.00 | August 2012 |
Multi-Purpose Assault Craft (MPAC) Lot 2 | 3 | P268,990,000.00 | November 2012 |